When to Order Restaurant Furniture Before Opening Day

Every restaurant opening has a critical path, and furniture is on it more often than owners expect. The kitchen equipment gets the attention. The furniture gets ordered “once the walls are up.” Then the booths are still in production two weeks before the soft opening.

The fix is simple: treat furniture like any other long-lead item and work backward from your opening date. Here’s a practical timeline, plus how to use quick ship and made-to-order products together so one late item doesn’t hold up the whole room.

Quick ship vs. made-to-order: know the difference

Quick ship products are standard items kept ready to ship in set sizes and finishes. Oak Street’s quick ship table tops include Urban, Woodland, Thermoform, 2-Sided and COMPCOR indoor/outdoor lines. They’re ideal when time is tight or you need to fill gaps.

Made-to-order products are built for your project: custom sizes, specific laminates or stains, booth lengths cut to your walls, upholstery in your brand colors. Oak Street’s made-to-order table tops, custom booths and casework fall here. They take longer, but they fit your space exactly.

Most successful openings use both. Custom booths and casework anchor the room. Quick ship tops and standard chairs fill in around them.

A working timeline (adjust to your project)

Lead times vary by product, season and order size, so confirm current timing with your account manager. Use this as a planning framework, counted back from opening day:

12–16 weeks out: Design and layout

  • Finalize the floor plan and seat count
  • Decide the booth, table and bar mix
  • Confirm ADA seating and aisle widths
  • Request samples of vinyl, laminate and stain

10–12 weeks out: Lock custom items

  • Approve booth drawings, lengths and shapes
  • Approve custom table sizes and finishes
  • Approve host stands, server stations and other casework
  • Place made-to-order orders

8–10 weeks out: Order standard items

  • Chairs and barstools
  • Table bases matched to every top size
  • Quick ship table tops
  • Outdoor furniture, if the patio opens with the restaurant

4–6 weeks out: Delivery planning

  • Confirm delivery date, address and contact
  • Arrange receiving: dock or liftgate, labor, storage
  • Make sure flooring and paint will be finished before booths go in

1–3 weeks out: Delivery and install

  • Inspect every shipment before signing
  • Install booths first, then set tables and chairs
  • Level every table where it sits

The five most common delays (and how to avoid them)

  1. Late design changes. Changing a booth length after approval can restart production. Lock the layout before you order.
  2. Finish decisions made too late. Waiting on a laminate or vinyl choice delays everything that uses it. Order samples early.
  3. Walls that don’t match the drawings. Field-measure after framing and before final booth approval.
  4. Receiving problems. Nobody on site, no liftgate, no room to stage pallets. Read Oak Street’s freight information before delivery day.
  5. Forgetting the small stuff. Waste receptacles, high chairs, host stands and server stations are easy to overlook until the week you open.

Use the free planning tools

Oak Street’s resource library is built for this phase:

FAQ

How far in advance should I order restaurant furniture? Start design 12–16 weeks before opening and place custom orders around 10–12 weeks out. Confirm current lead times with your supplier.

What is quick ship restaurant furniture? Standard items in set sizes and finishes that are ready to ship faster than made-to-order products.

Can I mix quick ship and custom furniture? Yes. Many openings use custom booths and casework with quick ship tops and standard seating.

Protect your opening date

Tell us your opening date and we’ll help you build a furniture plan that fits it. Request a quote, browse the digital product catalog, or call (877) 465-4344.